أول تركيب كندي لنظام PrimeSET™ أحادي الرحلة يبسط إنهاء Montney

40 Web Primeset St Liner Hanger

خلفية

Packers Plus has successfully completed the first installation of the PrimeSET™ Single Trip Liner Hanger in Canada’s Montney formation—a significant milestone for both the operator and Packers Plus, and a major step forward for the liner hanger industry. Designed for efficiency and reliability, the PrimeSET system streamlines operations and reduces rig time by enabling deployment on tie-back casing.

An operator in Canada had traditionally deployed open hole completion systems using a multi-trip method—setting the liner hanger, retrieving the running tool, performing a clean-out run (if required), and then deploying the upper completion assembly for stimulation. This standard procedure required 2–3 separate trips, adding rig time, fluid usage, and operational costs.

To address this inefficiency, Packers Plus introduced the PrimeSET™ Single Trip Liner Hanger system, engineered to streamline installation by enabling the deployment of both the lower and upper completions in a single trip. This approach saves time, reduces risk, and improves overall operational efficiency.

تحدي

طلب المشغل طريقة أكثر فعالية لنشر نظام الإكمال لتقليل الوقت والتكلفة. مع الإجراءات التقليدية التي تتطلب رحلات متعددة ووقتًا طويلاً للحفر، أصبحت الحاجة إلى حل مبسط أحادي الرحلة ذات أهمية متزايدة. في المواقع ذات النشاط العالي والحساسة للتكلفة مثل مونتني، يعد تعظيم كفاءة العمليات مع الحفاظ على الموثوقية أمرًا بالغ الأهمية.

حل

تضمن النظام أداة التشغيل القياسية للرحلة الواحدة (STRT) وتم استخدامه بنجاح لتركيب نظام إكمال الفتحة المفتوحة، وتثبيت معلق البطانة، وتحرير أداة التشغيل في عملية واحدة سلسة.

A minor procedural adjustment—releasing the STRT in compression, as recommended during the procedure review—was a key contributor to the success of the installation. The 5.0 in. deployment casing provided sufficient weight to effectively set the PrimeSET element, followed by a positive pressure test and successful annulus pressure test at 25 MPa (3,750 psi).

This installation eliminated two running trips, saving an estimated 12–18 hours of rig time and reducing the amount of fluid required for the operation.

نتائج

Close-up image of a sleek, silver dart with black grip rings on a white background.

أثبت التركيب القيمة التشغيلية والتجارية لـ PrimeSET Single Trip Liner Hanger:

  • توفير الوقت: تم استبعاد رحلتين، مما وفر ما يصل إلى 18 ساعة من وقت الحفر
  • توفير التكاليف خفض تكاليف تشغيل الحفارات واستخدام السوائل.
  • الموثوقية التشغيلية تطابقت نماذج عزم الدوران والسحب بشكل وثيق مع بيانات الوقت الفعلي، مما يؤكد الأداء المتوقع.
  • سهولة النشر تم تحقيقه مع انحراف ضئيل عن الإجراء المخطط له.
  • موثوقية الإعدادات المحسّنة The Packer Setting Sub—integrated into the OD of the setting mandrel and matching the casing OD—provided positive engagement and set-down force.
  • ظروف الثقب المواتية Contributed to operational success and demonstrated the system’s readiness for large-scale deployments worldwide.